If the action has no tasks or if the task weightings are not defined, then action progress is as per the 'Percent Complete' set for that particular action.
However, if the action has tasks defined and weightings are given, then action progress is calculated as follows:
Task |
Complete |
Weightings |
Task1 |
65 |
25 |
Task2 |
50 |
75 |
Action 'Percent Complete' = [(65*25) + (50*75)] / 100
![]() |
If an action has targets defined, then those targets are considered when calculating action progress. |
Action Progress Traffic Light Indicator
Action progress traffic light will display the following indication based on the 'Action Progress Threshold' configured within the configuration area.
On track -
Monitor -
Off Track -
|
Action Progress Traffic Light Indicator will display a blank traffic light in following instances
|