The Project report is designed to provide the users with the ability to extract all Project related information for a selected project from the system. This report includes details of all the project phases.
Filter |
Description |
Project |
Dropdown allows selection of an existing Project – list is ordered alphabetically by project name. 'Show All' is selected by default |
Project Type |
Dropdown selection of the Project Type. 'Show All' is selected by default |
Report Element |
Description |
project details | |
Ref | Displays the project reference number. (Defined within Proposal > Project Details area) |
Owner |
Displays the project owner’s name. (Defined within Proposal > Project Details area) |
Description |
Displays the project description. (Defined within Proposal > Project Details area) |
Parent Project |
Displays the name of the parent project this project belongs to (if available). (Defined within Proposal > Project Details area) |
Time Frame |
Displays the Start and Completion date. (Defined within Proposal > Project Details area) |
Project Type |
Displays the project type. (Defined within Proposal > Project Details area) |
Primary Strategy |
Displays the project’s primary strategy. (Defined within Proposal > Project Linkages > Initiative area) |
Project Expenditure | |
Expenditure |
Displays the expenditure title |
Description | Displays the expenditure description |
Weight |
Displays expenditure weightage |
Project Phases | |
Phase |
Displays the name of the phase |
From /To | Displays the phase’s Date To and Date From |
Project Linkage | |
Primary Strategy |
Displays the primary strategy which the project falls under. (Defined within Proposal > Project Linkages > Initiative area) |
Secondary Strategy |
Displays the multiple secondary strategies assigned to the project. (Defined within Proposal > Project Linkages > Initiative area) |
Funding Partners - Displays a list of funding partners assigned to the project | |
Preliminary Budget -Displays budget details defined within the Preliminary Budget tab in a table grid. | |
Project Board and Team | |
Project Member |
Displays staff name of projet member. (Defined in the Proposal > Project Board and Team) |
Project Position |
Displays the staff member’s position on this project’s board. (Defined in the Proposal > Project Board and Team) |
Implementation |
Indicates whether the staff member is in an implementation role or not. (Defined in the Proposal > Project Board and Team) |
Business case details | |
Project Purpose |
Displays the project’s purpose. (Defined in the Proposal > Business case area) |
Consultation | Displays the project consultation comment. (Defined in the Proposal > Business case area) |
Business Impact |
Displays the project’s business impact. (Defined in the Proposal > Business case area) |
Lessons from prior project | Displays the lessons learnt from prior projects. (Defined in the Proposal > Business case area) |
Project Objectives | |
Objective |
Displays the objective’s title |
Scale | Displays the scale defined for the objective |
Comments |
Displays objective’s comments |
Project Delivery Options - Displays a list of project delivery options | |
Project Outputs | |
Name |
Displays project output name. (Defined in the Proposal > Project outputs area) |
Description | Displays output description. (Defined in the Proposal > Project outputs area) |
Stakeholder Analysis-For each stakeholder assigned to the project, displays its name and each field configured beneath the stakeholder with the selection made for that field. (Defined in the proposal > Stakeholder analysis area) | |
Risk Assessment | |
Risk Issue |
Name of risk assessment. (Defined in Assessment >Risk Assessment area) |
Responsible Person | Staff member assigned as responsible person. (Defined in Assessment >Risk Assessment area) |
Causes | Causes identified. (Defined in Assessment >Risk Assessment area) |
Consequences | Consequences identified. (Defined in Assessment >Risk Assessment area) |
Risk category | Names of risk categories this risk is assigned to. (Defined in Assessment >Risk Assessment area) |
Issue Register | |
Issue Title |
Name of issue. (Defined in Planning >Issue register area) |
Responsible Person | Staff member assigned as responsible person. (Defined in Planning >Issue register area) |
Date Logged |
Logged date of issue. (Defined in Planning >Issue register area) |
Date Resolved | Resolved date of issue. (Defined in Planning >Issue register area) |
Status |
Issue status i.e. in progress, not started etc. (Defined in Planning >Issue register area) |
Resolution |
Issue resolution. (Defined in Planning >Issue register area) |
KPI's | |
KPI |
KPI title. (Defined in Assessment > KPIs > KPI Evaluation) |
Comments | KPI description. (Defined in Assessment > KPIs > KPI Evaluation) |
Responsible Officer |
Staff member assigned as responsible person. (Defined in Assessment > KPIs > KPI Evaluation) |
Unit | KPI unit. (Defined in Assessment > KPIs > KPI Evaluation) |
Target | KPI target. (Defined in Assessment > KPIs > KPI Evaluation) |
Actual |
KPI actual. (Defined in Assessment > KPIs > KPI Evaluation) |
Performance | Whether on track, off track or to monitor as indicated by image |
interplan link - Shows all linkages between this project and interplan | |
Task Planning | |
Task |
Name of task. (Defined in Assessment >Task planning) |
Comments | Shows task comments entered. (Defined in Assessment >Task planning) |
Start Date | Start Date of task. (Defined in Assessment >Task planning) |
End Date |
End Date of task. (Defined in Assessment >Task planning) |
Responsible Officer | Staff member assigned as responsible person. (Defined in Assessment > task planning area) |
% Completed | Issue status i.e. in progress, not started etc. (Defined in Assessment > task planning area) |