Allow Calculated Project Progress

If the check box is ticked, the project percentage complete will be auto-calculated using the average of task(s) percentage complete and the tasks will be equally weighted. However, the parent level task 'percentage complete' needs to be entered manually.

Example:

Task 1 - percent complete - 25%

Task 2 - percent complete - 25%

Project percent complete = (task 1+task 2)/2 = 25%

If it is not ticked, users will have to enter a project's overall percent complete manually to the percent complete field which can be made available from the project detail object as well as the quick update page.

Unticked by default.

 

 

 