Project Progress Calculation

Eg:

Time now = 26/9/12

Current baseline = Proposed (phase 2).

Task schedule is as follows:

Task

Scheduled Duration

Start Date

Finish Date

% complete

Task 1

100

17/07/2012

03/12/2012

0

Task 2

10

23/07/2012

03/08/2012

100

Task 3

10

30/07/2012

10/08/2012

100

 

Target = [ # Working days from current baseline start to Now/# Working days from current baseline start to finish]  *100

 =  [<17/7/ to 26/9> / <17/7 to 3/12>]*100

 =  [51/100] * 100

= 51%

Auto Achievement Progress Calculation Method

Actual = [ Working days from Actual start date to Now/ # Working days from forecast start to finish] * 100    

 = [<17/7/ to 26/9>/ <17/7 to 3/12>] * 100

 = [51/100] * 100

 = 51%

Performance = (Target/Actual) *100

   = (51/51) *100

   = 100%

Total Duration Calculation Method

Task Days complete = Sum [ (# Days for each task *% Complete)/100]

T1 : [(100*0)/100] = 0

T2: [(10*100)/100] = 10

T3: [(10*100)/100] = 10

Sum of task days = 20

Actual = [# Task Days Completed/ # Total Task Days Scheduled] * 100

= [20/120] *100

= 16.67%

Performance = (Actual/Target) *100

 = (16.67/51) *100

 = 32.68%

 

 

 

 