Eg:
Time now = 26/9/12
Current baseline = Proposed (phase 2).
Task schedule is as follows:
Task |
Scheduled Duration |
Start Date |
Finish Date |
% complete |
Task 1 |
100 |
17/07/2012 |
03/12/2012 |
0 |
Task 2 |
10 |
23/07/2012 |
03/08/2012 |
100 |
Task 3 |
10 |
30/07/2012 |
10/08/2012 |
100 |
Target = [ # Working days from current baseline start to Now/# Working days from current baseline start to finish] *100
= [<17/7/ to 26/9> / <17/7 to 3/12>]*100
= [51/100] * 100
= 51%
Auto Achievement Progress Calculation Method
Actual = [ Working days from Actual start date to Now/ # Working days from forecast start to finish] * 100
= [<17/7/ to 26/9>/ <17/7 to 3/12>] * 100
= [51/100] * 100
= 51%
Performance = (Target/Actual) *100
= (51/51) *100
= 100%
Total Duration Calculation Method
Task Days complete = Sum [ (# Days for each task *% Complete)/100]
T1 : [(100*0)/100] = 0
T2: [(10*100)/100] = 10
T3: [(10*100)/100] = 10
Sum of task days = 20
Actual = [# Task Days Completed/ # Total Task Days Scheduled] * 100
= [20/120] *100
= 16.67%
Performance = (Actual/Target) *100
= (16.67/51) *100
= 32.68%